PROJECT #1: Leak Detection Study
Project Goal: “To reduce the amount of water leaks in the distribution system.”
Project Objective:
1. Reduce the amount of water lost due to leaks in the system.
2. Pilot study of small area to determine benefit of the study.
Success Measurement: To reduce the amount of lost water.
Project Narrative: An older area of Marco Island will be selected and sound wave technology will be used to identify leaks. Once identified and determined the source and quantity of lost water then appropriate remedial action will be taken.
Five-Year Funding Recommendations
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
100,000 |
0 |
0 |
0 |
0 |
100,000 |
Funding: $50,000 Grant
$50,000 R & R
PROJECT #2: Facility Security
Project Goal: “Improve Security at the RO, Raw Water, and Lime Plant.”
Project Objective:
1. Install automated gates at the South Plant, Raw Water, and the North Plant.
2. Install electrically locked doors where rooms contain SCADA controls and are high traffic areas.
3. Install a security system at Raw Water.
4. Install new security fence at the South Plant.
Success Measurement: To have system installed by end of FY07.
Project Narrative: The U.S. “Bioterrorism Response Act of 2001, Title IV, Section 1433” requires water supplies to do a vulnerability assessment and to strengthen security at all the facilities used for the potable water production or distribution. A vulnerability assessment report for the City recommends strengthening (or hardening) our security system in a variety of ways.
1. Install new hardened, automated gates at the North, South, and Raw Water facilities. This will restrict access to employees and will allow other entrants to be screened before being allowed to enter.
2. Monitor security system at the Raw Water Lakes at 951 and US41. This facility supplies ½ of the potable water to Marco Island. In future scenarios, this location will possibly supply Marco residents with an increasing percentage of potable water, as well as irrigation water. The Marco Lakes are a surface water supply and as such have an increased vulnerability that wells do not have.
3. Improve fence line security by removing trees and vegetation, and replacing the top 3 strands of security wire.
4. Install proximity card entry doors where SCADA computers are used.
5. Install new fence at the South Plant and repair fence damaged by Hurricane Wilma at the North Plant and South Plant.
Five-Year Funding Recommendations
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
104,244 |
0 |
0 |
0 |
0 |
104,244 |
Funding: $104,244 R & R
PROJECT #3: Water System Renewal and Replacement
Project Goal: “To fund water distribution system repairs.”
Project Narrative: Historically, the utility experiences a variety of distribution and collection system repairs. These repairs are unplanned and in some cases unknown.
Examples of these events would be:
· Lightening strikes equipment or waterlines.
· Galvanized pipe taps corroding and breaking off.
· Random pipe breaks.
· Sink holes in street due to broken pipe.
Five-Year Funding Recommendations
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
515,000 |
530,450 |
546,364 |
562,754 |
579,637 |
2,734,205 |
Funding: $2,734,205 R & R
PROJECT #4: Dead End Line Flushing
Project Goal: “To provide a higher quality of water product to our customers. To be in compliance with FDEP dead-end flushing regulations FDEP Rules and Regulations, Chapter 62.555.”
Project Objective:
1. To install automatic or manual flushing facilities for all cul-de-sacs and dead-end water mains throughout Marco Island.
2. To comply with FDEP regulatory rule (62.555.350(2).
3. To provide consistent chlorine levels throughout the distribution system.
4. To reduce water quality complaints.
Success Measurement: To install flushing facilities in cul-de-sacs in FY07 based on available funds.
Project Narrative: Beginning in the year 2004, FDEP mandated that all dead end water mains should be flushed in accordance with the utilities written flushing program. The Utility has an active flushing program to fully meet the requirements set forth by DEP. Approximately 212 flush points need to be installed in the potable water system. This program will consist of excavating dead end lines and installing a manual or where appropriate an automatic method to flush these dead end water lines.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
|
50,000 |
|
0 |
0 |
50,000 |
Funding: $50,000 R & R
PROJECT #5: Meter Replacements
Project Goal: “To improve meter reading accuracy and reduce time needed to read the meters.”
Project Objective:
1. To replace/or retrofit current water meters with new touch pad read water meters.
Success Measurement: Convert 100% of the meters by the end of FY09.
Project Narrative: Water meter accuracy deteriorates with time. The normal life of a meter is 10 years. The Utility Department should replace approximately 10% per year. This has not been done in the past 3 years. FY06 provided funds to start the meter replacement program. Converting to “touch pad” reads will improve the accuracy of the readings.
Five-Year Funding Recommendations
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
0 |
0 |
250,000 |
250,000 |
300,000 |
800,000 |
Funding: $800,000 R & R
Project #6: Replace Water Treatment Plant Reverse Osmosis (RO) Membranes
Project Goal: “To continue the ongoing RO replacement/cleaning program.”
Project Objectives:
1. To replace one set (train) of RO membranes per year.
2. To chemically clean the remaining 5 membrane trains each year.
Success Measurements: Improve system reliability.
Project Narrative: The RO facility has 6 parallel treatment trains. Each train contains 24 membranes tubes. The source water is provided by 15 active brackish wells. This brackish well water enters a series of high-pressure vessels that operate at an elevated pressure. The membranes are located in the center of these vessels. A hydraulic pressure of 350-500 psi is applied to the source water and forced through the membrane pores. The membrane pore size is < .001 micron. This microscopic pore size is so small that it prevents 98% of the dissolved salt and other solids from passing through the membrane. As the membrane ages, the rejection level of the solids decreases, allowing more dissolved solids to pass through the treatment plant.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
348,175 |
319,612 |
348,420 |
350,000 |
365,000 |
1,731,207 |
Funding: $1,731,207 Capital Reserves
PROJECT #7: Capital Equipment
Project Goal:
· “To improve reliability of the System Control and Data Acquisition (SCADA) System, expand capabilities of the system, and reduce the number of customers inconvenienced by water shutdowns and subsequent boil water notices.”
Project Objective:
1. To improve reliability and operation confidence of the SCADA system.
2. To annually replace existing inoperable water distribution valves and install new isolation valves for the distribution systems.
3. Rehabilitate and upgrade one of the degasifiers to original specifications. Reduce emissions of hydrogen sulfide in the air at the RO Plant.
Success Measurement: To make initial improvements and establish a foundation, which will be improved in the following years.
Project Narrative: The current SCADA System is an old-style radio-polling system. The server polls hundreds of monitoring sites and does so one at a time. This slow polling causes various control problems or failed communication. The new system is “live” which means it virtually monitors all sites continuously. This allows the operators to monitor hundreds of remote sites with confidence and reliability. This in turn enables the Utility Department to monitor and control with less people and to do so reliably. Purchase various instruments and tools such as: low level TSS meter; ORP system for disinfection; chlorine meter; miscellaneous tools; trash pump; exhaust hood for lab; air chip hammer; air compressor; submersible hydro pump; pipe saw; valve machine;
maintenance crane; 500 gallon fuel tank on trailer; and miscellaneous supplies. Capital Equipment CIP includes funds for the following projects:
SCADA system upgrade |
$ 10,240 |
Inoperative Valves |
72,971 |
Maintenance Capital Equipment |
55,000 |
Collection & Distribution Capital Equipment |
50,000 |
Standby Generator |
100,000 |
Degasifier Replacement |
41,789 |
Five-Year Funding Recommendations
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
TOTAL |
615,000 |
275,000 |
0 |
0 |
0 |
700,230 |
Funding: $425,230 Capital Reserves
$275,000 Water Impact Fees
PROJECT #8: North Plant Site Preparations
Project Goal: “To prepare the previous County recycle facility for the new finished water storage tank and utilities facilities.”
Project Objectives:
1. Survey the facility site.
2. Identify stormwater management options.
3. Prepare site development plans.
Project’s Relationship to Utility Master Plan:
· The need for additional water treatment production and storage is clearly documented in the Master Plan.
Project Narrative: The new site will be used for finished water storage tanks, pump station, maintenance facility, and administration facilities. The site was acquired from Collier County in exchange for two parcels on Elkcam Circle (purchased by the City in FY06 for $1,450,000) and a parcel at Marco Shores adjacent to the Marco Island Airport. The site development plan will evaluate the feasibility of consolidating utility engineering, customer service, and plant maintenance and operation in one location. Currently the utility rents space for the utility engineering and customer service staff. The annual cost for rental is approximately $100,000.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
250,000 |
0 |
0 |
0 |
0 |
250,000 |
Funding: $250,000 Capital Reserves
Project #9: Pipeline Under Marco River
Project Goal: “To ensure an ample water supply for Marco Island.”
Project Objectives:
1. Design and construct a new 30-inch raw water pipeline under Marco River.
Project’s Relationship to Utility Master Plan:
· The need for this new River crossing was clearly documented in the Master plan, and has been reconfirmed by several Marco Island consulting firms.
Project Narrative: The current raw water supply line will not be capable of conveying additional raw water onto the Island. Additionally, the second raw water supply line will provide a measure of redundancy and reliability that doesn't exist currently.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
0 |
0 |
100,171 |
0 |
1,042,855 |
1,143,026 |
Funding: $1,143,026 Capital Reserves
Project #10: Vehicle Replacement Program
Project Goal: “To maintain the quality of the utility fleet.”
Project Objectives:
1. Replace approximately 50% of the utility fleet in FY10 and the balance in FY11.
Success Measurement: Replacement of approximately 50% of the utility fleet by the end of 2010.
Project Narrative: It is currently estimated that we will need to replace approximately 50% of the vehicle feet should be replaced in 2010.
All vehicles scheduled for replacement will be thoroughly evaluated for serviceability to ensure maximum appropriate cost/benefit.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
0 |
0 |
0 |
556,383 |
568,623 |
1,125,006 |
Funding: $1,125,006 Capital Reserves
Project #11: North Collier Water Line Upgrade
Project Goal: “To replace existing asbestos concrete pipe with plastic pipe.”
Project Objectives:
1. Replace existing old pipe with new pipe.
Project Narrative: The water lines under Collier Boulevard are being replaced as a component of the road improvement project.
Five-Year Funding Recommendation:
FY07 |
FY08 |
FY09 |
FY10 |
FY11 |
Total |
860,013 |
0 |
0 |
0 |
0 |
860,013 |
Funding: $860,013 Rate Base Bond Issue
Project #12: Finished Water Storage Tank
|