The City’s Water and Sewer Department is undertaking a Manhole Rehabilitation Project beginning July 21st. This project consists the repair and lining of existing manholes along Marco Lake Drive, Front Street, 1st Ave., 2nd Ave., 3rd Ave, Quail Drive, 5th Ave., 6th Ave., and Nassau Court. A total of 35 existing manholes and 208 vertical feet will be rehabilitated and repaired from July 21 - September 1, 2025. Work will take place between 7:00am and 3:00pm Monday – Friday. There will be no road closures, but there will be temporary lane closures on these streets. A map of the area is attached to this release.
Drivers should proceed through the area with caution and watch for workers in the street. There will be no impact to mail delivery or garbage pickup. For questions about this project, call City of Marco Island Water Sewer Department at 239-389-3930.